PMI-RMP Question #259: Real Exam Question with Answer & Explanation

The correct answer is B: Acceptance. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Which risk response is acceptable for both positive and negative risk events?

Options

  • ATransferring
  • BAcceptance
  • CSharing
  • DEnhancing

Topics

#Risk Response Strategies#Positive Risks#Negative Risks#Risk Acceptance

Community Discussion