PMI-RMP · Question #242

Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing…

The correct answer is A. Risk register. According to the PMBOK Guide, the Identify Risks process has a single output: the Risk Register. This is where the risk register is first created, containing the list of identified risks, potential risk owners, and potential risk responses. 'Risk register updates' (B) is the…

Risk Process Facilitation

Question

Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing that the risk identification process will create for Kelly?

Options

  • ARisk register
  • BRisk register updates
  • CChange requests
  • DProject document updates

How the community answered

(30 responses)
  • A
    90% (27)
  • B
    3% (1)
  • D
    7% (2)

Explanation

According to the PMBOK Guide, the Identify Risks process has a single output: the Risk Register. This is where the risk register is first created, containing the list of identified risks, potential risk owners, and potential risk responses. 'Risk register updates' (B) is the output of later risk processes (Qualitative/Quantitative Analysis, Plan Risk Responses) that update the already-created register. 'Change requests' (C) and 'Project document updates' (D) are outputs of other processes, not Identify Risks. The question specifically asks for the one thing it creates - that is the Risk Register itself.

Topics

#Risk Identification#Risk Register#Process Outputs#Project Documents