Question

You are the project manager of the NHQ Project for your company. You have completed qualitative and quantitative analysis of your identified project risks and you would now like to find an approach to increase project opportunities and to reduce threats within the project. What project management process would best help you?

Options

  • AMonitor and control project risks
  • BCreate a risk governance approach
  • CCreate the project risk register
  • DPlan risk responses

Topics

#Risk response planning#Threats and opportunities#Risk management processes#PMI-RMP

Community Discussion