PMIPMI
PMI-RMP · Question #241
PMI-RMP Question #241: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #241. The question stem and answer options stay visible for context.
Perform Targeted Risk Analysis
Question
Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?
Options
- AProject risks will increase.
- BThe project will take longer to complete, but risks will diminish.
- CProject costs will increase.
- DThe amount of hours a resource can be used will diminish.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Crashing#Schedule compression#Cost impact#Risk response