PMIPMI
PMI-RMP · Question #224
PMI-RMP Question #224: Real Exam Question with Answer & Explanation
The correct answer is B: You will need the risk register, risk management plan, project scope statement, and any relevant. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
You are the project manager of the BlueStar project in your company. Your company is structured as a functional organization and you report to the functional manager that you are ready to move onto the qualitative risk analysis process. What will you need as inputs for the qualitative risk analysis of the project in this scenario?
Options
- AQualitative risk analysis does not happen through the project manager in a functional structure.
- BYou will need the risk register, risk management plan, project scope statement, and any relevant
- CYou will need the risk register, risk management plan, outputs of qualitative risk analysis, and any
- DYou will need the risk register, risk management plan, permission from the functional manager, and any
Topics
#Qualitative Risk Analysis#Process Inputs#Risk Register#Risk Management Plan
Community Discussion
No community discussion yet for this question.