PMIPMI
PMI-RMP · Question #223
PMI-RMP Question #223: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #223. The question stem and answer options stay visible for context.
Risk Strategy and Planning
Question
Don has hired Jerry, a contractor, to complete a portion of his project work. The contract used was a cost-plus contract. If Don were to perform a risk audit, who would carry the risk in this scenario?
Options
- ADon would because he is the project manager.
- BJerry would because of the contract type.
- CDon would because of the contract type.
- DJerry would because he is the hired contractor.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Contract types#Cost-plus contract#Risk allocation#Procurement risk