nerdexam
PMIPMI

PMI-RMP · Question #225

PMI-RMP Question #225: Real Exam Question with Answer & Explanation

The correct answer is B: Four. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

You work as a project manager for TechSoft Inc. You are preparing to plan risk responses for your project with your project team. How many risk responses are available for a positive risk event in the project?

Options

  • AThree
  • BFour
  • CSeven
  • DOne

Topics

#Risk Response Strategies#Opportunity Management#Positive Risks#Planning Risk Responses

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions