PMIPMI
PMI-RMP · Question #225
PMI-RMP Question #225: Real Exam Question with Answer & Explanation
The correct answer is B: Four. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
You work as a project manager for TechSoft Inc. You are preparing to plan risk responses for your project with your project team. How many risk responses are available for a positive risk event in the project?
Options
- AThree
- BFour
- CSeven
- DOne
Topics
#Risk Response Strategies#Opportunity Management#Positive Risks#Planning Risk Responses
Community Discussion
No community discussion yet for this question.