Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement…

The correct answer is D. Look-up table. In PMI risk management, a look-up table (probability-impact matrix) is the specific tool used to convert assessed probability and impact values into a defined priority rating such as RAG status.

Perform Targeted Risk Analysis

Question

Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement among the project team as to how a certain risk is important and priority for attention should be managed. Where can Mark determine the priority of a risk given its probability and impact?

Options

  • ARisk management plan
  • BProject sponsor
  • CRisk response plan
  • DLook-up table

How the community answered

(27 responses)
  • A
    11% (3)
  • B
    7% (2)
  • C
    4% (1)
  • D
    78% (21)

Why each option

In PMI risk management, a look-up table (probability-impact matrix) is the specific tool used to convert assessed probability and impact values into a defined priority rating such as RAG status.

ARisk management plan

While the risk management plan contains the look-up table and defines how to use it, the plan is the broader document - the specific tool for determining individual risk priority is the look-up table itself.

BProject sponsor

The project sponsor does not determine individual risk priorities for specific risk events; that function belongs to the project team using defined risk tools.

CRisk response plan

The risk response plan documents planned responses after risks have been prioritized; it is not the source used to determine priority levels.

DLook-up tableCorrect

A look-up table, also known as a probability-impact matrix, is the direct tool used to convert a risk's assessed probability and impact values into a priority rating using predefined thresholds such as RAG (Red-Amber-Green) ratings. The project team references this table to objectively assign priority without subjective disagreement because the ratings are pre-established. This look-up table is defined within the risk management plan and is the specific artifact consulted for individual risk prioritization decisions.

Concept tested: Probability-impact matrix look-up table for risk prioritization

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk prioritization#Probability and impact matrix#Qualitative risk analysis#RAG rating