PMI-RMP · Question #177
Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement…
The correct answer is D. Look-up table. In PMI risk management, a look-up table (probability-impact matrix) is the specific tool used to convert assessed probability and impact values into a defined priority rating such as RAG status.
Question
Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement among the project team as to how a certain risk is important and priority for attention should be managed. Where can Mark determine the priority of a risk given its probability and impact?
Options
- ARisk management plan
- BProject sponsor
- CRisk response plan
- DLook-up table
How the community answered
(27 responses)- A11% (3)
- B7% (2)
- C4% (1)
- D78% (21)
Why each option
In PMI risk management, a look-up table (probability-impact matrix) is the specific tool used to convert assessed probability and impact values into a defined priority rating such as RAG status.
While the risk management plan contains the look-up table and defines how to use it, the plan is the broader document - the specific tool for determining individual risk priority is the look-up table itself.
The project sponsor does not determine individual risk priorities for specific risk events; that function belongs to the project team using defined risk tools.
The risk response plan documents planned responses after risks have been prioritized; it is not the source used to determine priority levels.
A look-up table, also known as a probability-impact matrix, is the direct tool used to convert a risk's assessed probability and impact values into a priority rating using predefined thresholds such as RAG (Red-Amber-Green) ratings. The project team references this table to objectively assign priority without subjective disagreement because the ratings are pre-established. This look-up table is defined within the risk management plan and is the specific artifact consulted for individual risk prioritization decisions.
Concept tested: Probability-impact matrix look-up table for risk prioritization