nerdexam
PMIPMI

PMI-RMP · Question #178

PMI-RMP Question #178: Real Exam Question with Answer & Explanation

The correct answer is A: They are the individuals that will need a sense of ownership and responsibility for the risk events.. See the full explanation below for the reasoning.

Stakeholder Engagement

Question

The Identify Risk process determines the risks that affect the project and document their characteristics. Why should the project team members be involved in the Identify Risk process?

Options

  • AThey are the individuals that will need a sense of ownership and responsibility for the risk events.
  • BThey are the individuals that will have the best responses for identified risks events within the project.
  • CThey are the individuals that are most affected by the risk events.
  • DThey are the individuals that will most likely cause and respond to the risk events.

Topics

#Identify Risk#Team Involvement#Risk Ownership#Responsibility

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions