nerdexam
PMIPMI

PMI-RMP · Question #176

PMI-RMP Question #176: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #176. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

You are the project manager of the NHH project for your company. You and the project team have completed the quantitative risk analysis for your project. During this process you create a contingency reserve based on the risk probability-impact matrix as seen in the figure below. Based on the information in the figure above, what amount would you need to include in your risk contingency fund?

Options

  • A-$465,000
  • B$171,500
  • C-$258,500
  • D$258,500

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Expected Monetary Value (EMV)#Contingency Reserve#Quantitative Risk Analysis#Risk Calculation
Full PMI-RMP PracticeBrowse All PMI-RMP Questions