nerdexam
PMI

PMI-RMP · Question #176

You are the project manager of the NHH project for your company. You and the project team have completed the quantitative risk analysis for your project. During this process you create a contingency…

The correct answer is D. $258,500. The quantitative risk contingency reserve is calculated using Expected Monetary Value (EMV), summing the products of each risk's probability and monetary impact to produce the total reserve amount.

Perform Targeted Risk Analysis

Question

You are the project manager of the NHH project for your company. You and the project team have completed the quantitative risk analysis for your project. During this process you create a contingency reserve based on the risk probability-impact matrix as seen in the figure below. Based on the information in the figure above, what amount would you need to include in your risk contingency fund?

Options

  • A-$465,000
  • B$171,500
  • C-$258,500
  • D$258,500

How the community answered

(64 responses)
  • A
    9% (6)
  • B
    3% (2)
  • C
    16% (10)
  • D
    72% (46)

Why each option

The quantitative risk contingency reserve is calculated using Expected Monetary Value (EMV), summing the products of each risk's probability and monetary impact to produce the total reserve amount.

A-$465,000

A negative contingency reserve value of -$465,000 is not a valid reserve amount; contingency reserves must be a positive value representing funds to be set aside for risk events.

B$171,500

$171,500 does not represent the correct EMV summation based on the probability-impact matrix values provided with the question.

C-$258,500

A negative value of -$258,500 is mathematically incorrect for a contingency reserve; the correct reserve is the positive equivalent representing funds to be allocated.

D$258,500Correct

The contingency reserve in quantitative risk analysis is determined by summing the Expected Monetary Value (EMV) of all identified risks, calculated as probability multiplied by monetary impact for each risk. A positive result of $258,500 represents the total reserve needed to cover probable risk impacts based on the probability-impact matrix data provided. This ensures the project has adequate funds set aside to address risks if they occur.

Concept tested: Expected Monetary Value calculation for contingency reserves

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Expected Monetary Value (EMV)#Contingency Reserve#Quantitative Risk Analysis#Risk Calculation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice