PMI-RMP · Question #175

What approach can a project manager use to improve the project's performance during qualitative risk analysis?

The correct answer is C. Focus on high-priority risks.. During qualitative risk analysis, focusing effort on high-priority risks ensures limited time and resources are directed toward the threats and opportunities that matter most to project objectives.

Perform Targeted Risk Analysis

Question

What approach can a project manager use to improve the project's performance during qualitative risk analysis?

Options

  • AFocus on near-term risks first.
  • BCreate a risk breakdown structure and delegate the risk analysis to the appropriate project team members.
  • CFocus on high-priority risks.
  • DAnalyze as many risks as possible regardless of who initiated the risk event.

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    79% (26)
  • D
    12% (4)

Why each option

During qualitative risk analysis, focusing effort on high-priority risks ensures limited time and resources are directed toward the threats and opportunities that matter most to project objectives.

AFocus on near-term risks first.

Focusing only on near-term risks ignores significant future risks that may carry high probability and impact, leading to an incomplete and potentially dangerous risk picture.

BCreate a risk breakdown structure and delegate the risk analysis to the appropriate project team members.

Delegating risk analysis via a risk breakdown structure may distribute workload but does not directly improve the quality or prioritization of the qualitative analysis process itself.

CFocus on high-priority risks.Correct

Focusing on high-priority risks during qualitative risk analysis allows the project manager to allocate analytical effort efficiently, ensuring that risks with the greatest potential impact on project objectives receive the most attention. This approach avoids diluting resources across low-value risks and improves overall analysis quality and the usefulness of risk response planning.

DAnalyze as many risks as possible regardless of who initiated the risk event.

Analyzing every possible risk regardless of source wastes resources on low-value items and reduces the overall quality and focus of the qualitative risk analysis process.

Concept tested: Qualitative risk analysis high-priority risk focus

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Qualitative Risk Analysis#Risk Prioritization#Project Performance#Risk Focus