PMIPMI
PMI-RMP · Question #175
PMI-RMP Question #175: Real Exam Question with Answer & Explanation
The correct answer is C: Focus on high-priority risks.. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
What approach can a project manager use to improve the project's performance during qualitative risk analysis?
Options
- AFocus on near-term risks first.
- BCreate a risk breakdown structure and delegate the risk analysis to the appropriate project team members.
- CFocus on high-priority risks.
- DAnalyze as many risks as possible regardless of who initiated the risk event.
Topics
#Qualitative Risk Analysis#Risk Prioritization#Project Performance#Risk Focus
Community Discussion
No community discussion yet for this question.