nerdexam
PMIPMI

PMI-RMP · Question #175

PMI-RMP Question #175: Real Exam Question with Answer & Explanation

The correct answer is C: Focus on high-priority risks.. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

What approach can a project manager use to improve the project's performance during qualitative risk analysis?

Options

  • AFocus on near-term risks first.
  • BCreate a risk breakdown structure and delegate the risk analysis to the appropriate project team members.
  • CFocus on high-priority risks.
  • DAnalyze as many risks as possible regardless of who initiated the risk event.

Topics

#Qualitative Risk Analysis#Risk Prioritization#Project Performance#Risk Focus

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions