The correct answer is B: Watchlist. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
Risks with low ratings of probability and impact are included on a ____ for future monitoring.
Options
- ARisk alarm
- BWatchlist
- CObservation list
- DRisk register
Topics
#Risk monitoring#Watchlist#Low priority risks#Risk management tools