PMI-RMP · Question #173

You are the project manager of a large construction project. Part of the project involves the wiring of the electricity in the building your project is creating. You and the project team determine…

The correct answer is C. Transference. Hiring a third-party contractor to perform dangerous work transfers the risk and its consequences to that external party, which is the definition of the transference response strategy.

Risk Strategy and Planning

Question

You are the project manager of a large construction project. Part of the project involves the wiring of the electricity in the building your project is creating. You and the project team determine the electrical work is too dangerous to perform yourself so you hire an electrician to perform the work for the project. This is an example of what type of risk response?

Options

  • AAcceptance
  • BMitigation
  • CTransference
  • DAvoidance

How the community answered

(33 responses)
  • A
    3% (1)
  • C
    91% (30)
  • D
    6% (2)

Why each option

Hiring a third-party contractor to perform dangerous work transfers the risk and its consequences to that external party, which is the definition of the transference response strategy.

AAcceptance

Acceptance means acknowledging the risk and deciding to deal with consequences if it occurs, rather than transferring responsibility to another party.

BMitigation

Mitigation reduces the probability or impact of a risk but does not shift ownership or liability to a third party.

CTransferenceCorrect

Risk transference shifts the financial impact and ownership of a risk to a third party without eliminating the risk itself. By hiring an electrician, the project transfers the danger and liability of the electrical work to the contractor, who assumes responsibility for managing that risk. This is a classic example of transference through outsourcing or contracting.

DAvoidance

Avoidance eliminates the risk entirely by changing the project plan, not by assigning the work and its associated risk to an outside contractor.

Concept tested: Risk transference via third-party contracting

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk response strategies#Risk transference#Procurement risk#Plan Risk Responses