PK0-003 · Question #293

A WBS dictionary:

The correct answer is B. provides a description of all of the components of a WBS, and a brief summary of its SOW, scope. A WBS dictionary provides detailed descriptions for each component of the Work Breakdown Structure, clarifying the work packages and their associated information.

Tools and documentation

Question

A WBS dictionary:

Options

  • Ais a granular hierarchical breakdown of the work to be undertaken by the project team, to meet
  • Bprovides a description of all of the components of a WBS, and a brief summary of its SOW, scope
  • Callocates the WBS components to appropriate teams or named individuals within teams.
  • Ddescribes how a project will be decomposed into smaller, manageable subprojects or work

How the community answered

(54 responses)
  • A
    2% (1)
  • B
    89% (48)
  • C
    2% (1)
  • D
    7% (4)

Why each option

A WBS dictionary provides detailed descriptions for each component of the Work Breakdown Structure, clarifying the work packages and their associated information.

Ais a granular hierarchical breakdown of the work to be undertaken by the project team, to meet

A is incorrect because it describes the WBS itself, which is a hierarchical breakdown of work, not the WBS dictionary that supplements it.

Bprovides a description of all of the components of a WBS, and a brief summary of its SOW, scopeCorrect

B is correct because the WBS dictionary serves as a companion to the WBS, providing detailed narrative descriptions for each work package and control account, including statements of work (SOW), scope, deliverables, and other relevant information to clarify the work involved. This ensures a common understanding of what each WBS element entails.

Callocates the WBS components to appropriate teams or named individuals within teams.

C is incorrect because resource allocation to teams or individuals is typically part of resource management planning, not the primary function of the WBS dictionary.

Ddescribes how a project will be decomposed into smaller, manageable subprojects or work

D is incorrect because it describes the process of decomposing a project, which is how a WBS is created, rather than the content of the WBS dictionary.

Concept tested: WBS dictionary purpose and components

Source: https://www.projectmanager.com/guides/wbs-dictionary

Topics

#WBS dictionary#scope definition#SOW