PK0-003 · Question #266

A change request has been reviewed and denied by the project governance. Which of the following components should be updated by the project manager?

The correct answer is B. Change log. When a change request is reviewed and denied by project governance, the project manager must update the change log to formally record the decision and maintain an accurate history of all change requests.

Tools and documentation

Question

A change request has been reviewed and denied by the project governance. Which of the following components should be updated by the project manager?

Options

  • AWBS
  • BChange log
  • CScope document
  • DCommunications log

How the community answered

(53 responses)
  • A
    4% (2)
  • B
    92% (49)
  • C
    2% (1)
  • D
    2% (1)

Why each option

When a change request is reviewed and denied by project governance, the project manager must update the change log to formally record the decision and maintain an accurate history of all change requests.

AWBS

The WBS (Work Breakdown Structure) would only be updated if a change request were approved and impacted the project's scope or work packages.

BChange logCorrect

The change log is the official repository for all change requests, regardless of their approval status, ensuring a comprehensive record of all proposed changes, their outcomes, and justifications. This maintains an audit trail and project transparency regarding all change management activities.

CScope document
DCommunications log

Concept tested: Project change management - documenting change decisions

Source: https://www.projectmanager.com/blog/change-log

Topics

#change log#change management#project documentation

Community Discussion

No community discussion yet for this question.