A change request has been submitted to the project manager containing the date, the details of the request, and the impact to the project. Which of the following needs to accompany the change request

The correct answer is B. Alternative options. For a change request to be thoroughly reviewed for consideration, it should include alternative options to enable a comprehensive evaluation and decision-making process by the project team.

Tools and documentation

Question

A change request has been submitted to the project manager containing the date, the details of the request, and the impact to the project. Which of the following needs to accompany the change request before it can be reviewed for consideration?

Options

  • AStakeholder sign-off
  • BAlternative options
  • CRequirements document
  • DCustomer acceptance

How the community answered

(52 responses)
  • A
    4% (2)
  • B
    87% (45)
  • C
    2% (1)
  • D
    8% (4)

Why each option

For a change request to be thoroughly reviewed for consideration, it should include alternative options to enable a comprehensive evaluation and decision-making process by the project team.

AStakeholder sign-off

Stakeholder sign-off typically occurs after a change request has been approved, not as a prerequisite for its initial review.

BAlternative optionsCorrect

Including alternative options helps the project team and change control board evaluate different ways to implement the change, understand their respective impacts, and choose the most suitable path. This ensures a thorough analysis beyond just the initial proposed solution, aiding the review for consideration.

CRequirements document
DCustomer acceptance

Concept tested: Project change management - change request components

Source: https://www.projectmanager.com/blog/change-management-process

Topics

#change request#change management process#alternative options