PK0-003 · Question #265
A change request has been submitted to the project manager containing the date, the details of the request, and the impact to the project. Which of the following needs to accompany the change request
The correct answer is B. Alternative options. For a change request to be thoroughly reviewed for consideration, it should include alternative options to enable a comprehensive evaluation and decision-making process by the project team.
Question
A change request has been submitted to the project manager containing the date, the details of the request, and the impact to the project. Which of the following needs to accompany the change request before it can be reviewed for consideration?
Options
- AStakeholder sign-off
- BAlternative options
- CRequirements document
- DCustomer acceptance
How the community answered
(52 responses)- A4% (2)
- B87% (45)
- C2% (1)
- D8% (4)
Why each option
For a change request to be thoroughly reviewed for consideration, it should include alternative options to enable a comprehensive evaluation and decision-making process by the project team.
Stakeholder sign-off typically occurs after a change request has been approved, not as a prerequisite for its initial review.
Including alternative options helps the project team and change control board evaluate different ways to implement the change, understand their respective impacts, and choose the most suitable path. This ensures a thorough analysis beyond just the initial proposed solution, aiding the review for consideration.
Concept tested: Project change management - change request components
Source: https://www.projectmanager.com/blog/change-management-process