To determine the MOST likely estimate for the length of project activities, a project manager would use which of the following?

The correct answer is A. PERT. A project manager would use the Program Evaluation and Review Technique (PERT) to calculate the most likely duration estimate for project activities, especially when there is uncertainty. PERT uses a weighted average of optimistic, pessimistic, and most likely estimates.

Tools and documentation

Question

To determine the MOST likely estimate for the length of project activities, a project manager would use which of the following?

Options

  • APERT
  • BGantt chart
  • CWBS Dictionary
  • DSPI

How the community answered

(26 responses)
  • A
    92% (24)
  • B
    4% (1)
  • D
    4% (1)

Why each option

A project manager would use the Program Evaluation and Review Technique (PERT) to calculate the most likely duration estimate for project activities, especially when there is uncertainty. PERT uses a weighted average of optimistic, pessimistic, and most likely estimates.

APERTCorrect

PERT (Program Evaluation and Review Technique) is a method used for activity duration estimation that considers three points (optimistic, pessimistic, and most likely) to calculate a weighted average, providing a more realistic and statistically derived "most likely estimate" for activity length, accounting for inherent uncertainties. This approach helps in producing a more accurate and reliable schedule baseline.

BGantt chart

A Gantt chart is a scheduling tool that visually represents project tasks and their dependencies over time, but it does not calculate activity duration estimates itself.

CWBS Dictionary

A WBS Dictionary provides detailed information about Work Breakdown Structure (WBS) elements but does not calculate activity duration estimates.

DSPI

SPI (Schedule Performance Index) is an Earned Value Management metric used to measure schedule efficiency and evaluate project performance, not to determine activity duration estimates.

Concept tested: Project activity duration estimation techniques

Topics

#PERT (Program Evaluation and Review Technique)#Activity duration estimation#Project scheduling