PK0-003 · Question #137
A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a certa
The correct answer is A. Time zones for various work locations. When a remote team member consistently submits late reports, the project manager should first investigate potential issues related to time zone differences. This is a common challenge in geographically distributed teams that can affect meeting times and deadlines.
Question
A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a certain time each week. One team member consistently submits late status reports. Which of the following should the project manager consider FIRST?
Options
- ATime zones for various work locations
- BNecessity of weekly status reports
- CFormat of the status report
- DPast performance reviews of the team member
How the community answered
(49 responses)- A80% (39)
- B12% (6)
- C6% (3)
- D2% (1)
Why each option
When a remote team member consistently submits late reports, the project manager should first investigate potential issues related to time zone differences. This is a common challenge in geographically distributed teams that can affect meeting times and deadlines.
Considering time zones is the first step because the "certain time each week" requirement might be based on the project manager's local time, which could be inconvenient or even an impractical time for a remote team member in a different time zone, leading to late submissions. Addressing this fundamental logistical issue is crucial for effective communication and collaboration in a distributed team.
While the necessity of weekly reports can be reviewed, it's not the first consideration for a consistent lateness issue; the immediate problem is adherence to an existing requirement.
The format of the report is unlikely to be the primary cause of consistent lateness, as the team member is submitting, just not on time.
Past performance reviews might provide context but are not the first proactive step to address a current, specific issue like late submissions, which could be easily resolved by adjusting for time zone differences.
Concept tested: Managing distributed teams and communication