nerdexam
PMI

PGMP · Question #430

The above performance report shows the earned value (EV) analysis for a program. The program director performs a high-level analysis and must present a summary narrative to the steering committee. Wha

The correct answer is D. Project A is running behind schedule and is over budget; projects B, C, and D are on. Based on the earned value analysis data in the performance report, Project A shows both a negative Schedule Performance Index (SPI < 1.0), indicating it is running behind schedule, and a negative Cost Performance Index (CPI < 1.0), indicating it is over budget. Projects B, C, and

Governance

Question

The above performance report shows the earned value (EV) analysis for a program. The program director performs a high-level analysis and must present a summary narrative to the steering committee. What do the current findings show?

Exhibit

PGMP question #430 exhibit

Options

  • AProject C is running behind schedule and is over budget; projects A, B, and D are on
  • BProject A is running ahead of schedule and is under budget; projects B, C, and D are behind
  • CThe overall program is performing within an acceptable level of variance.
  • DProject A is running behind schedule and is over budget; projects B, C, and D are on

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    15% (3)
  • C
    5% (1)
  • D
    75% (15)

Explanation

Based on the earned value analysis data in the performance report, Project A shows both a negative Schedule Performance Index (SPI < 1.0), indicating it is running behind schedule, and a negative Cost Performance Index (CPI < 1.0), indicating it is over budget. Projects B, C, and D show performance indices within acceptable variance ranges, meaning they are on or near their planned schedule and budget. Option A incorrectly identifies Project C as having problems. Option B incorrectly states Project A is ahead of schedule and under budget-the opposite of what the data shows. Option C overgeneralizes by stating the entire program is performing acceptably when Project A is clearly underperforming.

Topics

#Earned Value Management (EVM)#Performance Reporting#Program Governance#Variance Analysis

Community Discussion

No community discussion yet for this question.

Full PGMP Practice