nerdexam
PMI

PGMP · Question #127

Ben is the program manager for his organization. He's working with program team to determine what activities need to be completed in order to move the program into execution. He and the team are…

The correct answer is A. Work breakdown structure. This question tests the definition of a work breakdown structure (WBS) in program management. Decomposing program scope into smaller, manageable components produces a WBS.

Program Life Cycle

Question

Ben is the program manager for his organization. He's working with program team to determine what activities need to be completed in order to move the program into execution. He and the team are subdividing the program scope into smaller, manageable components to determine the activity list. What is Ben and his program team creating by subdividing the program scope in this scenario?

Options

  • AWork breakdown structure
  • BProgram network diagram
  • CProgram scope baseline
  • DActivity list

How the community answered

(19 responses)
  • A
    95% (18)
  • D
    5% (1)

Why each option

This question tests the definition of a work breakdown structure (WBS) in program management. Decomposing program scope into smaller, manageable components produces a WBS.

AWork breakdown structureCorrect

A work breakdown structure (WBS) is created by hierarchically decomposing the total scope of the program or project into smaller, manageable components called work packages. This decomposition process - subdividing scope - is the defining characteristic of WBS creation and is a foundational scope management technique that enables activity identification, estimating, and scheduling.

BProgram network diagram

A program network diagram represents the sequencing and dependencies of activities, not the hierarchical decomposition of scope into components.

CProgram scope baseline

The program scope baseline is a formal approved document consisting of the scope statement, WBS, and WBS dictionary - it is a result of planning, not the act of decomposing scope.

DActivity list

The activity list is derived from the WBS work packages but is a separate artifact - a list of schedule activities, not the hierarchical decomposition structure itself.

Concept tested: Work breakdown structure creation through scope decomposition

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Work Breakdown Structure#Program Scope Management#Program Planning#Scope Decomposition

Community Discussion

No community discussion yet for this question.

Full PGMP Practice