nerdexam
PMIPMI

PGMP · Question #126

PGMP Question #126: Real Exam Question with Answer & Explanation

The correct answer is A: The schedule to complete the work will take longer.. See the full explanation below for the reasoning.

Program Planning

Question

Wan is the program manager for his organization. He has been hearing reports that some project team members are complaining about the number of hours they're required to work on the program's projects and that some scheduling of team assignments are conflicting with their regular operational duties. You investigate the problem and agree that many team members are being assigned too much work within a given time period. You decide to enforce resource leveling heuristics to thirty hours of project work per week maximum. What will likely happen to the program and projects?

Options

  • AThe schedule to complete the work will take longer.
  • BThe cost of the program and project will increase.
  • CThe risks of failure will increase.
  • DThe morale of the project managers will decline.

Topics

#Resource Leveling#Schedule Management#Program Planning#Resource Management

Community Discussion

No community discussion yet for this question.

Full PGMP PracticeBrowse All PGMP Questions