nerdexam
PMI

PGMP · Question #121

You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling…

The correct answer is A. Mandatory dependencies. This question tests the distinction between mandatory and discretionary dependencies in project scheduling. Activities that must occur in a specific order due to the nature of the work are mandatory dependencies.

Program Planning

Question

You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that must happen in a particular order?

Options

  • AMandatory dependencies
  • BFinish on constraints
  • CBenefits management dependencies
  • DDiscretionary dependencies

How the community answered

(58 responses)
  • A
    88% (51)
  • B
    2% (1)
  • C
    7% (4)
  • D
    3% (2)

Why each option

This question tests the distinction between mandatory and discretionary dependencies in project scheduling. Activities that must occur in a specific order due to the nature of the work are mandatory dependencies.

AMandatory dependenciesCorrect

Mandatory dependencies, also called hard logic, are inherent to the work itself and cannot be reordered regardless of preference or resource availability. They are dictated by physical, legal, or contractual constraints - for example, a foundation must be poured before walls are built. These cannot be changed by the program manager without fundamentally altering the nature of the work.

BFinish on constraints

Finish-on constraints are scheduling constraints that fix an activity to end by a specific date, not a dependency type describing ordering relationships between activities.

CBenefits management dependencies

Benefits management dependencies is not a recognized term in program or project scheduling methodology.

DDiscretionary dependencies

Discretionary dependencies, also called soft logic or preferred logic, are based on best practices or preferences and CAN be reordered - they are the opposite of what the question describes.

Concept tested: Mandatory vs. discretionary scheduling dependencies

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Program Schedule Management#Activity Dependencies#Mandatory Dependencies#Program Planning

Community Discussion

No community discussion yet for this question.

Full PGMP Practice