PGMP · Question #239
PGMP Question #239: Real Exam Question with Answer & Explanation
The correct answer is B: Staffing pool description. See the full explanation below for the reasoning.
Program Planning
Question
You are the program manager for your organization. Your program is about to being initiated and management is asking you for a document that will define all of the required resources, skills, and competencies you'll need in your program. What document defines the skills and competencies for a program?
Options
- AStaffing management plan
- BStaffing pool description
- CProgram resources requirements plan
- DHuman resources management plan
Topics
#Program Planning#Human Resources#Resource Management#Skills & Competencies