Portfolio Communication Management

Question

During a governance meeting, a functional manager introduced a new collaboration software to improve communication. You learned that this software could raise the effectiveness of portfolio communication management. Which item should you update to capture this founding?

Options

  • AOrganizational process assets
  • BPortfolio communication management plan
  • CEnterprise environmental factors
  • DPortfolio process assets

Unlock PFMP to see the answer

You've previewed enough free PFMP questions. Unlock PFMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Portfolio Communication Management#Portfolio Process Assets#Tools and Techniques#Knowledge Management
Full PFMP PracticeBrowse All PFMP Questions