Your company got recently acquired by another company and the strategic directions which your portfolio is based on have been changed. Which document do you, as a portfolio manager, change to reflect

The correct answer is A. Communication Management Plan. When an acquisition introduces new stakeholders with changed expectations, the Communication Management Plan must be updated to capture and address those new communication requirements.

Portfolio Communication Management

Question

Your company got recently acquired by another company and the strategic directions which your portfolio is based on have been changed. Which document do you, as a portfolio manager, change to reflect the new stakeholders and their expectations?

Options

  • ACommunication Management Plan
  • BPortfolio Roadmap
  • CPortfolio Strategic Plan
  • DPortfolio Management Plan

How the community answered

(29 responses)
  • A
    76% (22)
  • B
    14% (4)
  • C
    7% (2)
  • D
    3% (1)

Why each option

When an acquisition introduces new stakeholders with changed expectations, the Communication Management Plan must be updated to capture and address those new communication requirements.

ACommunication Management PlanCorrect

The Communication Management Plan identifies stakeholders, their information needs, and how communications will be managed throughout the portfolio lifecycle. After an acquisition brings new stakeholders with different expectations, this plan must be revised to incorporate those parties, their requirements, preferred channels, and engagement strategies.

BPortfolio Roadmap

The Portfolio Roadmap depicts the high-level timeline and sequencing of portfolio components, not stakeholder communication needs.

CPortfolio Strategic Plan

The Portfolio Strategic Plan defines strategic goals and investment allocation aligned to organizational strategy, not the communication requirements of specific stakeholders.

DPortfolio Management Plan

The Portfolio Management Plan is a broad document covering all management areas; stakeholder-specific communication requirements are captured in the Communication Management Plan.

Concept tested: Portfolio Communication Management Plan stakeholder updates

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Communication Management#Stakeholder Engagement#Portfolio Planning#Organizational Change