You are performing a readiness assessment to assess how ready the organization is to serve the steps necessary to bridge the gap between the "as-is" portfolio state and the "to-be" state. Which proces

The correct answer is B. Manage Strategic Change. Performing a readiness assessment to evaluate the organization's capacity to bridge the gap between the current 'as-is' and desired 'to-be' portfolio states is part of the 'Manage Strategic Change' process.

Portfolio Performance

Question

You are performing a readiness assessment to assess how ready the organization is to serve the steps necessary to bridge the gap between the "as-is" portfolio state and the "to-be" state. Which process are you performing?

Options

  • AOptimize Portfolio
  • BManage Strategic Change
  • CDevelop Portfolio Roadmap
  • DDevelop Portfolio Strategic Plan

How the community answered

(28 responses)
  • A
    11% (3)
  • B
    82% (23)
  • C
    4% (1)
  • D
    4% (1)

Why each option

Performing a readiness assessment to evaluate the organization's capacity to bridge the gap between the current 'as-is' and desired 'to-be' portfolio states is part of the 'Manage Strategic Change' process.

AOptimize Portfolio

'Optimize Portfolio' focuses on balancing and adjusting the component mix for maximum strategic value - it does not involve organizational readiness assessments.

BManage Strategic ChangeCorrect

The 'Manage Strategic Change' process involves assessing organizational readiness for change and determining what steps are needed to transition from the current portfolio state to the target future state. Readiness assessments are a key activity in this process, as they evaluate whether the organization has the capability, culture, and capacity to execute the strategic changes required by the portfolio.

CDevelop Portfolio Roadmap

'Develop Portfolio Roadmap' creates a visual timeline of portfolio components mapped to strategic goals - it does not assess organizational readiness for change.

DDevelop Portfolio Strategic Plan

'Develop Portfolio Strategic Plan' establishes the strategic direction and goals of the portfolio - it precedes readiness assessment rather than containing it.

Concept tested: Manage Strategic Change readiness assessment

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management