PFMP · Question #299

A portfolio manager needs to continuously balance the need and requirements with the available resources and needs to maintain a balanced portfolio and portfolio resources in order to optimize deliver

The correct answer is B. Roadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, Portfolio Process Assets. The process described - continuously balancing needs/requirements with available resources and optimizing delivery - is 'Manage Supply and Demand.' Its inputs include the Roadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, and Portfolio Process Assets. Option B corr

Portfolio Performance

Question

A portfolio manager needs to continuously balance the need and requirements with the available resources and needs to maintain a balanced portfolio and portfolio resources in order to optimize delivery. For this, you are always on the lookout to optimize your portfolio. What can you use to start this process?

Options

  • ARoadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, Enterprise Environmental
  • BRoadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, Portfolio Process Assets
  • CRoadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, Portfolio Organizational
  • DRoadmap, Portfolio Strategic Plan, Portfolio, Portfolio Reports, Portfolio Process Assets

How the community answered

(52 responses)
  • A
    4% (2)
  • B
    71% (37)
  • C
    15% (8)
  • D
    10% (5)

Explanation

The process described - continuously balancing needs/requirements with available resources and optimizing delivery - is 'Manage Supply and Demand.' Its inputs include the Roadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, and Portfolio Process Assets. Option B correctly identifies Portfolio Process Assets (templates, historical data, lessons learned) as a key input that supports this optimization process. Options A, C, and D substitute incorrect elements: Enterprise Environmental Factors, Portfolio Organizational Process Assets (a non-standard term), or Portfolio Strategic Plan in place of the Portfolio Management Plan.

Topics

#Portfolio Optimization#Portfolio Management Inputs#Portfolio Management Plan#Organizational Process Assets