PFMP · Question #519

You have set a meeting with your portfolio team members as an answer to the identification and update of the organization near-term budget and plans. One of your team members asked you of the goal of

The correct answer is D. Developing specific portfolio assets. A team meeting convened to identify and update near-term budgets and plans is focused on developing specific portfolio assets, not on higher-level authorization or initiation activities.

Portfolio Performance

Question

You have set a meeting with your portfolio team members as an answer to the identification and update of the organization near-term budget and plans. One of your team members asked you of the goal of what is being done. Your answer to him should be

Options

  • AAll of the options
  • BAuthorizing the portfolio
  • CInitiating the portfolio
  • DDeveloping specific portfolio assets

How the community answered

(55 responses)
  • A
    4% (2)
  • B
    15% (8)
  • C
    9% (5)
  • D
    73% (40)

Why each option

A team meeting convened to identify and update near-term budgets and plans is focused on developing specific portfolio assets, not on higher-level authorization or initiation activities.

AAll of the options

Not all options simultaneously describe this activity; the meeting's specific purpose is asset development, not a combined exercise of authorizing, initiating, and developing assets at the same time.

BAuthorizing the portfolio

Authorizing the portfolio is a formal governance decision made by the Portfolio Governance Board or Sponsor, not an outcome of a team budget identification and planning meeting.

CInitiating the portfolio

Initiating the portfolio refers to the formal start-up phase that produces the portfolio charter; ongoing budget and planning update meetings occur well after initiation is complete.

DDeveloping specific portfolio assetsCorrect

When the portfolio team meets to identify and update near-term budgets and operational plans, the activity produces specific portfolio assets - documents, estimates, and plans that support ongoing portfolio execution. This is an asset development activity within portfolio management, distinct from the authorization or initiation phases which involve governance-level decisions by the Governance Board or Sponsor.

Concept tested: Goal of near-term budget and plan identification meetings

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Management#Strategic Alignment#Portfolio Components#Performance Management