PFMP · Question #184

An input to the process to optimize the portfolio is:

The correct answer is A. portfolio process assets. Portfolio process assets - templates, historical information, and documented procedures - are an established input to the portfolio optimization process.

Portfolio Performance

Question

An input to the process to optimize the portfolio is:

Options

  • Aportfolio process assets.
  • Bthe portfolio charter.
  • Ccapability and capacity analysis.
  • Dquantitative and qualitative analysis.

How the community answered

(30 responses)
  • A
    93% (28)
  • C
    3% (1)
  • D
    3% (1)

Why each option

Portfolio process assets - templates, historical information, and documented procedures - are an established input to the portfolio optimization process.

Aportfolio process assets.Correct

Portfolio process assets encompass existing policies, procedures, templates, and lessons learned that guide how portfolio optimization is conducted. They are a standard input in the PMI portfolio management framework, providing the organizational knowledge base from which the optimization process draws.

Bthe portfolio charter.

The portfolio charter is an input to the defining and aligning process groups, not specifically to the optimization process.

Ccapability and capacity analysis.

Capability and capacity analysis is a tool and technique used within portfolio management processes, not an input to portfolio optimization.

Dquantitative and qualitative analysis.

Quantitative and qualitative analysis are tools and techniques applied during portfolio optimization, not inputs to it.

Concept tested: Inputs to the portfolio optimization process

Source: https://www.pmi.org/pmbok-guide-standards/framework/portfolio-management

Topics

#Portfolio Optimization#Portfolio Management Inputs#Organizational Process Assets#PMI PFMP