A portfolio manager is currently in the defining phase of a portfolio that aligns to a new organizational strategy. The portfolio manager is beginning to develop the portfolio charter, but is having d

The correct answer is A. Capability and capacity. During portfolio charter development in the defining phase, capability and capacity analysis validates that the organization can realistically execute the proposed portfolio components.

Strategic Alignment

Question

A portfolio manager is currently in the defining phase of a portfolio that aligns to a new organizational strategy. The portfolio manager is beginning to develop the portfolio charter, but is having difficulty ensuring that it is complete, comprehensive, and accurate. As part of the portfolio charter development, the portfolio manager should perform which type of analysis?

Options

  • ACapability and capacity
  • BInterdependency
  • CComponent inventory
  • DComponent prioritization

How the community answered

(36 responses)
  • A
    81% (29)
  • B
    6% (2)
  • C
    3% (1)
  • D
    11% (4)

Why each option

During portfolio charter development in the defining phase, capability and capacity analysis validates that the organization can realistically execute the proposed portfolio components.

ACapability and capacityCorrect

Capability and capacity analysis assesses the organization's current and projected ability to deliver in terms of skills, resources, and bandwidth. Performing this analysis during charter development ensures the charter's commitments are grounded in organizational reality, making the document complete, comprehensive, and accurate.

BInterdependency

Interdependency analysis examines relationships between components and is typically performed after components are identified and authorized, not during initial charter development.

CComponent inventory

Component inventory is an input that lists existing components; it is not an analysis technique used to ensure charter completeness.

DComponent prioritization

Component prioritization occurs after the charter is developed and components are identified; it is a subsequent activity, not part of charter development.

Concept tested: Capability and capacity analysis in portfolio charter development

Source: https://www.pmi.org/pmbok-guide-standards/framework/portfolio-management

Topics

#Portfolio Charter#Portfolio Defining Phase#Capability and Capacity Analysis#Strategic Alignment

Community Discussion

No community discussion yet for this question.

Full PFMP Practice