The correct answer is D: Organizational process assets. See the full explanation below for the reasoning.

Strategic Alignment

Question

Which of the following is not an input for "Develop Portfolio Charter"?

Options

  • APortfolio strategic plan
  • BPortfolio process assets
  • CEnterprise environmental factors
  • DOrganizational process assets

Topics

#Portfolio Charter#Process Inputs#Portfolio Management Processes#Organizational Process Assets