nerdexam
Microsoft

MB-910 · Question #26

All employees at a company work eight hours each day Monday through Friday. A resource named Resource1 has 40 hours available for a specific week. You need to schedule Resource1 to work on a project…

The correct answer is D. Front-load hours. You would have to create separate bookings for each of the working days. https://docs.microsoft.com/en-us/dynamics365/project-operations/psa/faq-allocation-methods

Submitted by deeparc· Apr 18, 2026Explore the core capabilities of customer engagement apps in Dynamics 365

Question

All employees at a company work eight hours each day Monday through Friday. A resource named Resource1 has 40 hours available for a specific week. You need to schedule Resource1 to work on a project during that week. The resource must work the hours detailed below: Which allocation method should you use?

Options

  • ARemaining capacity
  • BPercentage capacity
  • CFull capacity
  • DFront-load hours

How the community answered

(55 responses)
  • A
    15% (8)
  • B
    4% (2)
  • C
    9% (5)
  • D
    73% (40)

Explanation

You would have to create separate bookings for each of the working days. https://docs.microsoft.com/en-us/dynamics365/project-operations/psa/faq-allocation-methods

Topics

#Resource allocation#Project scheduling#Capacity planning#Front-load scheduling

Community Discussion

No community discussion yet for this question.

Full MB-910 Practice