Microsoft
MB-910 · Question #26
All employees at a company work eight hours each day Monday through Friday. A resource named Resource1 has 40 hours available for a specific week. You need to schedule Resource1 to work on a project…
The correct answer is D. Front-load hours. You would have to create separate bookings for each of the working days. https://docs.microsoft.com/en-us/dynamics365/project-operations/psa/faq-allocation-methods
Submitted by deeparc· Apr 18, 2026Explore the core capabilities of customer engagement apps in Dynamics 365
Question
All employees at a company work eight hours each day Monday through Friday. A resource named Resource1 has 40 hours available for a specific week. You need to schedule Resource1 to work on a project during that week. The resource must work the hours detailed below: Which allocation method should you use?
Options
- ARemaining capacity
- BPercentage capacity
- CFull capacity
- DFront-load hours
How the community answered
(55 responses)- A15% (8)
- B4% (2)
- C9% (5)
- D73% (40)
Explanation
You would have to create separate bookings for each of the working days. https://docs.microsoft.com/en-us/dynamics365/project-operations/psa/faq-allocation-methods
Topics
#Resource allocation#Project scheduling#Capacity planning#Front-load scheduling
Community Discussion
No community discussion yet for this question.