MB-910 · Question #120
A customer creates a new project in Dynamics 365 Project Operations. The customer needs to add project work items. You need to specify the duration of the work. Where should you specify the duration…
The correct answer is C. Tasks. In Dynamics 365 Project Operations, the project schedule is built using Tasks (part of the Work Breakdown Structure). Each task has a Duration field where you specify how long that unit of work will take. Estimates are used for cost and resource projections, Summary rows roll…
Question
Options
- AEstimates
- BSummary
- CTasks
- DResource assignments
How the community answered
(25 responses)- A4% (1)
- C96% (24)
Explanation
In Dynamics 365 Project Operations, the project schedule is built using Tasks (part of the Work Breakdown Structure). Each task has a Duration field where you specify how long that unit of work will take. Estimates are used for cost and resource projections, Summary rows roll up data from child tasks, and Resource Assignments link team members to tasks - but none of these are where you define duration directly. Duration is an attribute of the Task itself.
Topics