MB-910 · Question #120

A customer creates a new project in Dynamics 365 Project Operations. The customer needs to add project work items. You need to specify the duration of the work. Where should you specify the duration…

The correct answer is C. Tasks. In Dynamics 365 Project Operations, the project schedule is built using Tasks (part of the Work Breakdown Structure). Each task has a Duration field where you specify how long that unit of work will take. Estimates are used for cost and resource projections, Summary rows roll…

Submitted by tarun92· Apr 18, 2026Explore the core capabilities of customer engagement apps in Dynamics 365

Question

A customer creates a new project in Dynamics 365 Project Operations. The customer needs to add project work items. You need to specify the duration of the work. Where should you specify the duration of the work?

Options

  • AEstimates
  • BSummary
  • CTasks
  • DResource assignments

How the community answered

(25 responses)
  • A
    4% (1)
  • C
    96% (24)

Explanation

In Dynamics 365 Project Operations, the project schedule is built using Tasks (part of the Work Breakdown Structure). Each task has a Duration field where you specify how long that unit of work will take. Estimates are used for cost and resource projections, Summary rows roll up data from child tasks, and Resource Assignments link team members to tasks - but none of these are where you define duration directly. Duration is an attribute of the Task itself.

Topics

#Dynamics 365 Project Operations#Project tasks#Work breakdown structure#Task duration

Community Discussion

No community discussion yet for this question.