MB-910 · Question #83

A company is implementing Dynamics 365 Project Operations to manage projects for customers. You are training project managers on how to enter statements of work into the new system. You need to ensure

The correct answer is A. Project contracts. In Dynamics 365 Project Operations, the project managers would need to enter the required information for the number of hours and the hourly rate for each item in the "Project Contract" or "Project Task" entities. This can be done by creating a new project contract/ task record a

Submitted by saadiq_pk· Apr 18, 2026Explore the core capabilities of customer engagement apps in Dynamics 365

Question

A company is implementing Dynamics 365 Project Operations to manage projects for customers. You are training project managers on how to enter statements of work into the new system. You need to ensure that the number of hours and the hourly rate for each item are entered. Where must the project managers enter the required information?

Options

  • AProject contracts
  • BProject stages
  • CProject accounting
  • DResource management
  • EProject tracking

How the community answered

(51 responses)
  • A
    88% (45)
  • B
    6% (3)
  • C
    4% (2)
  • E
    2% (1)

Explanation

In Dynamics 365 Project Operations, the project managers would need to enter the required information for the number of hours and the hourly rate for each item in the "Project Contract" or "Project Task" entities. This can be done by creating a new project contract/ task record and filling in the relevant fields such as "Estimated Hours" and "Estimated Cost" for each item.

Topics

#Dynamics 365 Project Operations#Project Contracts#Statements of Work#Pricing