MB-910 · Question #24
A company plans to implement Dynamics 365 Project Operations. Which two billing methods does Dynamics 365 Project Operations support? Each correct answer presents a complete solution. NOTE: Each…
The correct answer is A. Time and Material B. Fixed Price. Dynamics 365 Project Operations supports two contract billing methods: Time and Material (T&M), where the customer is billed based on actual hours worked and materials consumed, and Fixed Price, where a set contract amount is agreed upon regardless of actual effort or cost…
Question
Options
- ATime and Material
- BFixed Price
- CExpense
- DNot-to-exceed Limit
How the community answered
(46 responses)- A91% (42)
- C7% (3)
- D2% (1)
Explanation
Dynamics 365 Project Operations supports two contract billing methods: Time and Material (T&M), where the customer is billed based on actual hours worked and materials consumed, and Fixed Price, where a set contract amount is agreed upon regardless of actual effort or cost. 'Expense' is a transaction type or category within a project, not a billing method. 'Not-to-exceed Limit' is a cap or constraint that can be applied to a T&M contract to limit total billing, but it is not a standalone billing method.
Topics
Community Discussion
No community discussion yet for this question.