ITIL-FOUNDATION · Question #434
How does Problem Management work with Change Management?
The correct answer is C. By issuing RFCs for permanent solutions. Problem Management works with Change Management by raising Requests for Change (RFCs) to implement permanent fixes for identified root causes.
Question
How does Problem Management work with Change Management?
Options
- ABy installing changes to fix problems
- BBy negotiating with Incident Management for changes in IT for Problem resolution
- CBy issuing RFCs for permanent solutions
- DBy working with users to change their IT configurations
How the community answered
(23 responses)- A4% (1)
- B4% (1)
- C78% (18)
- D13% (3)
Why each option
Problem Management works with Change Management by raising Requests for Change (RFCs) to implement permanent fixes for identified root causes.
Installing changes is the responsibility of Change Management and Release Management, not Problem Management.
Problem Management does not negotiate with Incident Management for changes; it raises RFCs directly to Change Management for formal authorization.
In ITIL, Problem Management is responsible for diagnosing root causes of incidents and proposing permanent solutions. When a permanent fix is determined, Problem Management raises an RFC to Change Management, which then governs the formal assessment, authorization, and controlled implementation of that fix. This separation ensures problem resolution does not bypass the change control process.
Problem Management does not work with end users to alter their personal IT configurations; it focuses on identifying and eliminating root causes of infrastructure-level or systemic problems.
Concept tested: Problem Management RFC process for permanent solutions
Source: https://www.axelos.com/certifications/itil-service-management/itil-4-foundation
Topics