ISEB-PM1 · Question #630

A new manufacturing facility is being built for a consumer electronic company. The project to create it is nearing completion and will soon begin to enter the Closing phase. This will involve a…

The correct answer is B. The customer. See the full explanation below for the reasoning.

The Project Management Lifecycle

Question

A new manufacturing facility is being built for a consumer electronic company. The project to create it is nearing completion and will soon begin to enter the Closing phase. This will involve a number of people, but who will ultimately approve the work of the project?

Options

  • AProject Manager
  • BThe customer
  • CSenior management
  • DStakeholders

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    83% (19)
  • C
    4% (1)
  • D
    9% (2)

Topics

#project closure#customer approval#closing phase#stakeholder roles

Community Discussion

No community discussion yet for this question.