The sponsor on the airport runway project has just told the Project Manager about a change he wants. He says that the change will cost 20% less and should not cause any problems to the existing…

The correct answer is D. Scope and schedule impact. See the full explanation below for the reasoning.

Project Control

Question

The sponsor on the airport runway project has just told the Project Manager about a change he wants. He says that the change will cost 20% less and should not cause any problems to the existing environment. Which of the following should concern the Project Manager the most?

Options

  • AScope impact
  • BSchedule impact
  • CQuality impact
  • DScope and schedule impact

How the community answered

(20 responses)
  • A
    5% (1)
  • C
    10% (2)
  • D
    85% (17)

Topics

#integrated change control#scope impact#schedule impact#change management