What is used to define the accounts that the WBS and organizational structures align to for project cost tracking?

The correct answer is B. Chart of accounts. You've hit your weekly limit · resets 5am (America/New_York)

Project Planning

Question

What is used to define the accounts that the WBS and organizational structures align to for project cost tracking?

Options

  • AWork packages
  • BChart of accounts
  • CCost estimates
  • DCost baseline

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    73% (27)
  • C
    14% (5)
  • D
    8% (3)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#chart of accounts#cost tracking#WBS alignment#cost management