ISEB-PM1 · Question #633
You are the Project Manager on a merger and acquisition project. Activity A (3 days. and activity B (4 days. can start immediately. Activity C (2 days. can start after A and B are complete. Activity…
The correct answer is C. BEGH. You've hit your weekly limit · resets 5am (America/New_York)
Question
You are the Project Manager on a merger and acquisition project. Activity A (3 days. and activity B (4 days. can start immediately. Activity C (2 days. can start after A and B are complete. Activity D (5 days. can begin after activity B is complete. Activity E (6 days. can begin after activity B is complete. Activity F (4 days. can begin after activities C and D are complete. Activity G (5 days. can begin after activities D and E are complete. Activity H (4 days. can begin after activities F and G are complete. What is the critical path?
Options
- ABCFH
- BBDFH
- CBEGH
- DACFH
How the community answered
(21 responses)- A5% (1)
- B10% (2)
- C81% (17)
- D5% (1)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
Community Discussion
No community discussion yet for this question.