ISEB-PM1 · Question #633

You are the Project Manager on a merger and acquisition project. Activity A (3 days. and activity B (4 days. can start immediately. Activity C (2 days. can start after A and B are complete. Activity…

The correct answer is C. BEGH. You've hit your weekly limit · resets 5am (America/New_York)

Project Planning

Question

You are the Project Manager on a merger and acquisition project. Activity A (3 days. and activity B (4 days. can start immediately. Activity C (2 days. can start after A and B are complete. Activity D (5 days. can begin after activity B is complete. Activity E (6 days. can begin after activity B is complete. Activity F (4 days. can begin after activities C and D are complete. Activity G (5 days. can begin after activities D and E are complete. Activity H (4 days. can begin after activities F and G are complete. What is the critical path?

Options

  • ABCFH
  • BBDFH
  • CBEGH
  • DACFH

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    10% (2)
  • C
    81% (17)
  • D
    5% (1)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#critical path method#network diagram#schedule analysis#CPM calculation