All of the following could be considered functions of the GERT diagramming method except?

The correct answer is B. Some activities may be fast tracked. You've hit your weekly limit · resets 5am (America/New_York)

Project Planning

Question

All of the following could be considered functions of the GERT diagramming method except?

Options

  • ASome activities may be performed only in part
  • BSome activities may be fast tracked
  • CSome activities may be performed more than once
  • DSome activities may not be performed

How the community answered

(54 responses)
  • A
    4% (2)
  • B
    83% (45)
  • C
    4% (2)
  • D
    9% (5)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#GERT diagramming#network diagramming#schedule techniques#conditional branching