All of the following could be considered functions of the GERT diagramming method except?
The correct answer is B. Some activities may be fast tracked. You've hit your weekly limit · resets 5am (America/New_York)
Project Planning
Question
All of the following could be considered functions of the GERT diagramming method except?
Options
- ASome activities may be performed only in part
- BSome activities may be fast tracked
- CSome activities may be performed more than once
- DSome activities may not be performed
How the community answered
(54 responses)- A4% (2)
- B83% (45)
- C4% (2)
- D9% (5)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#GERT diagramming#network diagramming#schedule techniques#conditional branching