BCS-ISEB
ISEB-PM1 · Question #583
The project manager is assigned in the?
The correct answer is C. Charter (contract). You've hit your weekly limit · resets 5am (America/New_York)
The Project Management Lifecycle
Question
The project manager is assigned in the?
Options
- AManagement Plan
- BSOW
- CCharter (contract)
- DProject Plan
How the community answered
(44 responses)- A11% (5)
- B5% (2)
- C82% (36)
- D2% (1)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#project charter#project manager assignment#project initiation#project authorization