Parametric Estimating is done as a part of which process:
The correct answer is A. Estimate Activity Durations. ISEB ISEB-PM1 Exam
Project Planning
Question
Parametric Estimating is done as a part of which process:
Options
- AEstimate Activity Durations
- BSequence Activities
- CDevelop Schedule
- DEstimate Activity Resources
How the community answered
(31 responses)- A81% (25)
- B10% (3)
- C6% (2)
- D3% (1)
Explanation
ISEB ISEB-PM1 Exam
Topics
#parametric estimating#activity duration#estimating techniques#schedule management