Parametric Estimating is done as a part of which process:

The correct answer is A. Estimate Activity Durations. ISEB ISEB-PM1 Exam

Project Planning

Question

Parametric Estimating is done as a part of which process:

Options

  • AEstimate Activity Durations
  • BSequence Activities
  • CDevelop Schedule
  • DEstimate Activity Resources

How the community answered

(31 responses)
  • A
    81% (25)
  • B
    10% (3)
  • C
    6% (2)
  • D
    3% (1)