Which of the following correctly explains the term "progressive elaboration"?

The correct answer is D. Project specifications becoming more explicit and detailed as the project progresses. Progressive elaboration refers to the iterative process where project details become increasingly specific and refined as more information becomes available over time - making option D the only accurate definition. Option A is wrong because progressive elaboration is not about…

The Project Management Lifecycle

Question

Which of the following correctly explains the term "progressive elaboration"?

Options

  • AChanging project specifications continuously
  • BElaborate tracking of the project progress
  • CElaborate tracking of the project specifications with a change control system
  • DProject specifications becoming more explicit and detailed as the project progresses

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    13% (4)
  • C
    3% (1)
  • D
    77% (24)

Explanation

Progressive elaboration refers to the iterative process where project details become increasingly specific and refined as more information becomes available over time - making option D the only accurate definition.

Option A is wrong because progressive elaboration is not about changing specifications arbitrarily; it's about refining them as understanding deepens. Option B mistakes "elaborate" as an adjective (meaning detailed/thorough tracking) rather than a verb (to develop further), making it a word-trap. Option C compounds that same error and conflates the concept with change control, which is a separate process governing approved changes to scope.

Memory tip: Break down the phrase literally - progressive means "advancing over time," and elaborate means "to develop in greater detail." Together: details advance and grow over time. Think of it like a map coming into focus as you zoom in - you always knew the destination, but the route becomes clearer as you move forward.

Topics

#progressive elaboration#scope definition#project planning concepts#terminology