ISEB-PM1 · Question #270

A Project Management Office (PMO) manages a number of aspects, including what?

The correct answer is D. Overall risk, overall opportunity and interdependencies among projects. A PMO operates at a program or portfolio level, making its primary role one of governance across multiple projects - managing overall risk, opportunities, and interdependencies among those projects (D). It provides the strategic oversight layer that individual project managers…

Organizational Aspects of Project Management

Question

A Project Management Office (PMO) manages a number of aspects, including what?

Options

  • AProject scope, schedule, cost, and quality of the products of the work packages
  • BCentral coordinator of communication management across projects, and for the delivery of
  • CAssigns project resources to best meet project objectives
  • DOverall risk, overall opportunity and interdependencies among projects

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    3% (1)
  • C
    13% (4)
  • D
    77% (23)

Explanation

A PMO operates at a program or portfolio level, making its primary role one of governance across multiple projects - managing overall risk, opportunities, and interdependencies among those projects (D). It provides the strategic oversight layer that individual project managers cannot, since they're focused on their own project scope.

Why the distractors are wrong:

  • A describes what an individual project manager controls - scope, schedule, cost, and quality sit within a single project, not across the PMO's domain.
  • B is partially true (a PMO does coordinate communication), but it's an incomplete and secondary function, not the defining one the question targets.
  • C describes a resource manager role, not a PMO function - resource allocation to meet objectives is typically handled at the functional or resource management level.

Memory tip: Think of the PMO as the "air traffic control tower" - it doesn't fly any individual plane (project), but it manages the overall airspace: which flights (projects) create conflicts, what risks exist across all routes, and how to coordinate them safely. The key word in the correct answer is "interdependencies" - that cross-project coordination is the PMO's signature responsibility.

Topics

#PMO#project management office#portfolio interdependencies#program governance