nerdexam
BCS-ISEB

ISEB-PM1 · Question #269

Which of the following is a project constraint?

The correct answer is D. The product is needed in 250 days. Option D is correct because a project constraint is a fixed limitation that bounds the project's execution - a hard deadline of 250 days directly restricts when the project must be completed, making it a classic time constraint (one of the triple constraints: scope, time…

Project Planning

Question

Which of the following is a project constraint?

Options

  • ATwenty-five percent staff turnover is expected.
  • BThe technology to be used is cutting-edge.
  • CProject leadership may change due to volatile political environment.
  • DThe product is needed in 250 days.

How the community answered

(46 responses)
  • A
    9% (4)
  • B
    17% (8)
  • C
    2% (1)
  • D
    72% (33)

Explanation

Option D is correct because a project constraint is a fixed limitation that bounds the project's execution - a hard deadline of 250 days directly restricts when the project must be completed, making it a classic time constraint (one of the triple constraints: scope, time, cost).

  • A is wrong because staff turnover is a risk - an uncertain event that may occur and could impact the project, not a firm boundary imposed on it.
  • B is wrong because cutting-edge technology is an assumption or potentially a risk/complexity factor - it describes the nature of the work, not a binding limitation.
  • C is wrong because potential leadership change is also a risk - it's conditional ("may change") rather than a defined, fixed constraint.

Memory tip: Think of constraints as things someone outside the project team has already decided for you - budget caps, fixed deadlines, regulatory requirements. If it says "may" or "expected," it's a risk, not a constraint. Constraints are certain; risks are uncertain.

Topics

#project constraints#constraint vs assumption#schedule constraint#project definition

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice