Which of the following is a project constraint?
The correct answer is D. The product is needed in 250 days. Option D is correct because a project constraint is a fixed limitation that bounds the project's execution - a hard deadline of 250 days directly restricts when the project must be completed, making it a classic time constraint (one of the triple constraints: scope, time…
Question
Which of the following is a project constraint?
Options
- ATwenty-five percent staff turnover is expected.
- BThe technology to be used is cutting-edge.
- CProject leadership may change due to volatile political environment.
- DThe product is needed in 250 days.
How the community answered
(46 responses)- A9% (4)
- B17% (8)
- C2% (1)
- D72% (33)
Explanation
Option D is correct because a project constraint is a fixed limitation that bounds the project's execution - a hard deadline of 250 days directly restricts when the project must be completed, making it a classic time constraint (one of the triple constraints: scope, time, cost).
- A is wrong because staff turnover is a risk - an uncertain event that may occur and could impact the project, not a firm boundary imposed on it.
- B is wrong because cutting-edge technology is an assumption or potentially a risk/complexity factor - it describes the nature of the work, not a binding limitation.
- C is wrong because potential leadership change is also a risk - it's conditional ("may change") rather than a defined, fixed constraint.
Memory tip: Think of constraints as things someone outside the project team has already decided for you - budget caps, fixed deadlines, regulatory requirements. If it says "may" or "expected," it's a risk, not a constraint. Constraints are certain; risks are uncertain.