Which of the following methods is a project selection technique?

The correct answer is C. Cost-benefit analysis. Cost-benefit analysis (C) is a project selection technique because it evaluates whether a project's expected benefits outweigh its costs, helping organizations decide which projects to pursue before committing resources. Flowcharting (A) is a process mapping tool used to…

The Project Management Lifecycle

Question

Which of the following methods is a project selection technique?

Options

  • AFlowcharting
  • BEarned value
  • CCost-benefit analysis
  • DPareto analysis

How the community answered

(39 responses)
  • A
    3% (1)
  • B
    13% (5)
  • C
    77% (30)
  • D
    8% (3)

Explanation

Cost-benefit analysis (C) is a project selection technique because it evaluates whether a project's expected benefits outweigh its costs, helping organizations decide which projects to pursue before committing resources. Flowcharting (A) is a process mapping tool used to visualize workflows - it's used during or after project planning, not to select projects. Earned value (B) is a performance measurement technique that compares planned vs. actual progress on an in-progress project. Pareto analysis (D) is a quality/prioritization tool (the 80/20 rule) used to identify the most impactful problems, but it doesn't evaluate whether to initiate a project.

Memory tip: Think "selection = before you start." Only cost-benefit analysis answers the question "Should we do this project at all?" - the others are tools used once work has already begun.

Topics

#project selection#cost-benefit analysis#feasibility#project initiation