While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
Options
- AUtilize the change control process.
- BCrash the schedule to fix the defect.
- CLeave the defect in and work around it.
- DFast-track the remaining development.
Unlock ISEB-PM1 to see the answer