Which tool is used to develop technical details within the project management plan?
The correct answer is A. Expert Judgment. Expert Judgment is correct because it is a key tool and technique in the Develop Project Management Plan process (PMBOK). When the project manager needs to define technical details - such as tailoring methodologies, setting baselines, or determining how plans integrate - they…
Question
Which tool is used to develop technical details within the project management plan?
Options
- AExpert Judgment
- BProject Management Methodology
- CProject Management Information
- DProject Selection Methods
How the community answered
(51 responses)- A80% (41)
- B6% (3)
- C2% (1)
- D12% (6)
Explanation
Expert Judgment is correct because it is a key tool and technique in the Develop Project Management Plan process (PMBOK). When the project manager needs to define technical details - such as tailoring methodologies, setting baselines, or determining how plans integrate - they rely on individuals or groups with specialized knowledge to inform those decisions.
Why the distractors are wrong:
- B. Project Management Methodology is an input to developing the plan (it provides a framework to follow), not a tool used to develop technical details.
- C. Project Management Information System (PMIS) is a tool for storing, retrieving, and distributing project information - it supports execution and monitoring, not the crafting of technical details in planning.
- D. Project Selection Methods (e.g., NPV, scoring models) are used before a project begins to decide which projects to pursue - they have no role inside the planning process.
Memory tip: Think of it this way - whenever PMBOK asks "how do you figure out the hard stuff?", the answer is almost always Expert Judgment. It's the universal planning tool; if you see "develop," "define," or "determine technical details," Expert Judgment is the safe bet.
Topics
Community Discussion
No community discussion yet for this question.