The correct answer is B. Performing the activities included in the plan.. See the full explanation below for the reasoning.
Question
What is the definition of project plan execution?
Options
- AIntegrating all planned activities.
- BPerforming the activities included in the plan.
- CDeveloping and maintaining the plan.
- DExecution of deliverables.