The correct answer is B. Performing the activities included in the plan.. See the full explanation below for the reasoning.

Question

What is the definition of project plan execution?

Options

  • AIntegrating all planned activities.
  • BPerforming the activities included in the plan.
  • CDeveloping and maintaining the plan.
  • DExecution of deliverables.